Progress Report on Rehab of Residences

Residences (upstairs) are the first priority towards habitation; the goal is to secure occupation permits by July 1, 2018.

Beth repairs the plaster walls, plasters the drywall, lays flooring (using the wood found in the building), and continues work with local contractors to install and update HVAC, plumbing, and electricity throughout the building.

Precise Plumbing connecting the building to city water:new water line 4new water line day two b

plastering the walls:

DSCN0493DSCN0494DSCN0495DSCN0496

scrap wood used to build out the bathroom in 6911:DSCN0497

Bathroom floor in 6911:DSCN0498DSCN0500

kitchen flooring and plumbing cabinets in 6911:DSCN0502

kitchen flooring and cabinet-in-progress in 6913:DSCN0503DSCN0506

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

A WordPress.com Website.

Up ↑

%d bloggers like this: